Project Details

Project Details
Agency King Co.
Project # C171002
Project Title SE Green Valley Rd & 218th Ave SE I/S
WSDOT Region Northwest
Legislative District 031
Congressional District 08
Project Description Construct a single-lane roundabout. Improvements will include roadway reconstruction, cement concrete curb, marked crosswalks, shoulders, signs & markings, drainage improvements, bioswale and/or retention pond, landscaping, erosion/sediment control, and illumination.
Project Type Design
Project Funding
Fund ProgramAmount
STP Regional$366,760.00
Federal Total$366,760.00
Other$57,240.00
Total Project Cost (see NOTE below)$424,000.00
Project Milestones
Preliminary Engineering Authorized 12-22-2021
Environmental Approved
Right of Way Certified
Construction Authorized
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.