Project Details

Project Details
Agency Davenport
Project # 0310005
Project Title Sports Complex Trail Phase 2
WSDOT Region Eastern
Legislative District 013
Congressional District 05
Project Description Construct a pedestrian trail parallel to SR 25 from the end of the Phase 1 trail (approx. SR 25, MP 0.34) to US 2.
Project Type Transportation Enhancement
Project Funding
Fund ProgramAmount
TAP$279,871.00
Federal Total$279,871.00
Other$95,009.00
Total Project Cost (see NOTE below)$374,880.00
Project Milestones
Preliminary Engineering Authorized 08-18-2021
Environmental Approved 12-30-2025
Right of Way Certified 01-28-2026
Construction Authorized 09-03-2026
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed