Project Details

Project Details
Agency Clarkston
Project # 5975003
Project Title 13th Street Roundabouts
WSDOT Region South Central
Legislative District 009
Congressional District 05
Project Description Construct mini roundabouts at the intersections of 13th Street and Poplar Street, and 13th St and Highland Ave. Improvements at both intersections include updated ADA ramps, pedestrian refuge islands, updated signage, pavement markings, new asphalt surfacing, stamped concrete splitter islands, and RRFB’s.
Project Type Preservation
Project Funding
Fund ProgramAmount
Carbon Reduction$122,067.00
STP Regional$1,472,155.00
Federal Total$1,594,222.00
Other$53,000.00
Total Project Cost (see NOTE below)$1,647,222.00
Project Milestones
Preliminary Engineering Authorized 08-05-2021
Environmental Approved 08-07-2025
Right of Way Certified 05-05-2026
Construction Authorized 09-02-2026
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.