Project Description Reconstruct roadway and include sidewalks, curb and gutter, on-street parking, and a bike lane.
Project Type Preservation
Project Funding
Fund ProgramAmount
Highway Infrastructure Program$71,921.00
LP Federal - Additional OA$1,600,000.00
STP Regional$1,064,887.00
Federal Total$2,736,808.00
Other$850,782.00
Total Project Cost (see NOTE below)$3,587,590.00
Project Milestones
Preliminary Engineering Authorized 07-22-2021
Environmental Approved 02-21-2025
Right of Way Certified 06-25-2025
Construction Authorized 08-27-2025
Completed