Project Details

Project Details
Agency Edmonds
Project # 9931021
Project Title 76th Ave. W @ 220th St. SW Intersection
WSDOT Region Northwest
Legislative District 021
Congressional District 07
Project Description Widen the intersection on all approaches to add turn lanes and construct wider sidewalks. Work includes new traffic signal system, lighting, signage, pavement, pavement striping, utility improvements, and potential conversion of overhead utility lines to underground.
Project Type Design
Project Funding
Fund ProgramAmount
CMAQ$702,000.00
Federal Total$702,000.00
Other$232,000.00
Total Project Cost (see NOTE below)$934,000.00
Project Milestones
Preliminary Engineering Authorized 01-04-2021
Environmental Approved
Right of Way Certified
Construction Authorized
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.