Project Details

Project Details
Agency Monroe
Project # 2673001
Project Title 147th Signal
WSDOT Region Northwest
Legislative District 039
Congressional District 02
Project Description Install traffic signal at intersection 147th St. and 179th Ave in Monroe. To include ADA ramps, APS (Pedestrian Signals), widening to accommodate truck traffic, provide dedicated left turn lane on 147th, pavement markings as necessary and remove existing mid-block ADA ramps.
Project Type Improvement
Project Funding
Fund ProgramAmount
CMAQ$665,000.00
STP Regional$116,813.00
Federal Total$781,813.00
Other$785,368.00
Total Project Cost (see NOTE below)$1,567,181.00
Project Milestones
Preliminary Engineering Authorized 07-21-2020
Environmental Approved 05-23-2024
Right of Way Certified 05-31-2024
Construction Authorized 09-09-2024
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.