Project Details

Project Details
Agency Kitsap Co.
Project # 2018062
Project Title Taylor Road Bridge
WSDOT Region Olympic
Legislative District 035
Congressional District 06
Project Description Prepare and paint the steel girders and deck soffitt of the bridge superstructure.
Project Type Bridge
Project Funding
Fund ProgramAmount
Bridge$672,755.65
Federal Total$672,755.65
Other$76,019.26
Total Project Cost (see NOTE below)$748,774.91
Project Milestones
Preliminary Engineering Authorized 09-23-2020
Environmental Approved 03-15-2022
Right of Way Certified
Construction Authorized 05-03-2022
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.