Project Details

Project Details
Agency Cowlitz Co.
Project # 2008033
Project Title Allender Road Bridge
WSDOT Region Southwest
Legislative District 019
Congressional District 03
Project Description Replace existing bridge with a new structure. Reconstruct approaches, as necessary.
Project Type Bridge
Project Funding
Fund ProgramAmount
Bridge$2,417,546.00
Federal Total$2,417,546.00
Other$0.00
Total Project Cost (see NOTE below)$2,417,546.00
Project Milestones
Preliminary Engineering Authorized 09-09-2020
Environmental Approved 05-16-2023
Right of Way Certified 10-04-2024
Construction Authorized 09-04-2025
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.