Agency
Bothell
Project #
2570012
Project Title
228th Street - 35th to 39th
WSDOT Region
Northwest
Legislative District
001
Congressional District
01
Project Description
Widen 228th Street from three to four lanes. Includes intersection improvements, curbs, gutters, sidewalks, non-motorized facilities, lighting, signals, and signal interconnect.
Project Type
Right of Way
Project Funding
Fund Program
Amount
STP Regional
$1,836,275.00
Federal Total
$1,836,275.00
Other
$1,772,056.00
Total Project Cost (see NOTE below)
$3,608,331.00
Project Milestones
Preliminary Engineering Authorized
07-31-2019
Environmental Approved
09-14-2023
Right of Way Certified
Construction Authorized
Completed
Roads
Satellite
JavaScript must be enabled in order for you to use this map.
However, it seems JavaScript is either disabled or not supported by your browser. To view this map, enable JavaScript by changing your browser options, and then try again.
LEGEND:
Design
Right of Way
Construction
Complete
Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.