Project Details

Project Details
Agency Snoqualmie
Project # 0202060
Project Title Town Center Phase 3 Improvements
WSDOT Region Northwest
Legislative District 005
Congressional District 08
Project Description Replace existing trail bridge, improve lane width, intersection channelization, utilities, sidewalks, transit facilities, ADA ramps, lighting, and pavement on SR 202 (Railroad Ave SE) between SE Northern St and SE 69th PL.
Project Type Design
Project Funding
Fund ProgramAmount
STP Regional$392,590.57
Federal Total$392,590.57
Other$61,271.36
Total Project Cost (see NOTE below)$453,861.93
Project Milestones
Preliminary Engineering Authorized 07-24-2019
Environmental Approved
Right of Way Certified
Construction Authorized
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.