Project Details

Project Details
Agency Auburn
Project # 0164020
Project Title Auburn Way S. (SR 164) - Hemlock to Poplar
WSDOT Region Northwest
Legislative District 031
Congressional District 08
Project Description Widen Auburn Way S between Hemlock St SE and Poplar St SE, sidewalks, bus pull-outs, street lighting' stormwater, eastbound turnaround, and enhanced pedestrian crossing near Redwood Court.
Project Type Improvement
Project Funding
Fund ProgramAmount
STP Regional$7,352,500.00
Federal Total$7,352,500.00
Other$2,507,807.00
Total Project Cost (see NOTE below)$9,860,307.00
Project Milestones
Preliminary Engineering Authorized 07-24-2019
Environmental Approved 03-08-2023
Right of Way Certified 12-03-2024
Construction Authorized 12-13-2024
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.