Project Details

Project Details
Agency WSDOT (SW)
Project # PB19011
Project Title WSDOT: SR 4 Signing and Channelization Road Diet
WSDOT Region Southwest
Legislative District 019
Congressional District 03
Project Description Road reconfiguration, speed feedback signs, school speed zone signage, crosswalks, pedestrian refuge island, pedestrian activated flashing beacons, buffered bike lanes.
Project Type Safety
Project Funding
Fund ProgramAmount
Pedestrian & Bicycle Safety$556,618.68
State Total$556,618.68
Other$0.00
Total Project Cost (see NOTE below)$556,618.68
Project Milestones
Preliminary Engineering Authorized 01-22-2020
Environmental Approved
Right of Way Certified
Construction Authorized 04-19-2021
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.