Agency Clarkston
Project # 9902036
Project Title Bridge St/Diagonal St/2nd St Intersection
WSDOT Region South Central
Legislative District 009
Congressional District 05
Project Description Construct roundabout at intersection of Bridge Street / Diagonal Street / 2nd Street.
Project Type Preservation
Project Funding
Fund ProgramAmount
Highway Infrastructure Program$54,279.00
HSIP$1,936,646.00
STP Regional$2,280,276.00
Federal Total$4,271,201.00
Other$474,804.00
Total Project Cost (see NOTE below)$4,746,005.00
Project Milestones
Preliminary Engineering Authorized 05-24-2019
Environmental Approved 04-13-2021
Right of Way Certified 12-22-2022
Construction Authorized 03-16-2023
Completed
LEGEND:  Design  Right of Way  Construction  Complete  Delayed
NOTE: Total project cost only reflects the current costs for the project milestones authorized above. For example, if construction is not authorized, the total project cost shown does not include costs to construct.